NOTICE OF POWER INTERRUPTION. September 29, 2016 (Thursday)



DATE: September 29, 2016 (Thursday)


PURPOSE:
A) Preparatory works for the energization of the new 100MVA power transformer at Nagsaag Substation; Disconnection of temporary connection of San Manuel-Calasiao69kV Line from Nagsaag Substation; Shifting of power source of San Manuel-Calasiao 69kV Line from Nagsaag Substation back to San Manuel Substation
B) Transmission line activities relative to the shifting of power source of San Manuel-Umingan 69kV Line from San Manuel 100MVA Power Transformer to the new 100MVA Power Transformer at Nagsaag Substation; Shifting of power source of San Manuel-Umingan 69kV Line to the new 10MVA Power Transformer at Nagsaag Substation
AFFECTED AREAS: 


A) 6:00AM - 12:00Noon
URDANETA CITY - Poblacion, Dilan-Paurido, San Vicente, Anonas, Tulong, Catablan, Labit West, Cabaruan, Oltama, Sugcong, Mabanogbog,, Nancamaliran East/West, Pinmaludpod, San Jose, Cayambanan, Nancalobasaan, Camantiles, Bayaoas 


Inamotan, Manaoag
La Paz, VILLASIS
ASINGAN - Calepaan, Palaris, Toboy, Sobol, Coldit, Bobonan
MAPANDAN, BINALONAN, SAN MANUEL, POZORRUBIO, LAOAC


B) 6:00AM - 2:00PM
B) URDANETA CITY - Nancayasan, Camanang, Consolacion, Macalong, Tipuso, Portion of Paurido, Dilan, Sto. Domingo, Sta. Lucia, Palina Central/East/West, Labit Proper/East, Cabuloan, Casantaan, Bolaoen, PT Orata, Bactad East 

Portion of Bacag, VILLASIS
ASINGAN except Calepaan, Palaris, Toboy, Sobol, Coldit, Bobonan
ROSALES, VILLASIS, STO. TOMAS, BALUNGAO, TAYUG, STA. MARIA, NATIVIDAD, SAN NICOLAS, SAN QUINTIN, UMINGAN

All works may be finished ahead of time and power may be restored earlier than scheduled, so please consider our lines and equipment energized at all times.

Source: PANELCO III Official FB 

Comments