POWER INTERRUPTION ADVISORY:
The National Grid Corporation of the Philippines (NGCP) serves notice
of the scheduled shutdown of some of its transmission facilities in
these areas:
Date: 24 November 2012
Time: 7:00 AM – 5:00 PM
Affected Distribution Utility: * Parts PANELCO III and CENPELCO
Affected areas: * San Manuel, Binalonan, Pozorrubio, Laoac, Mapandan and parts of Sison, Urdaneta and Asingan
Reason: Continuation of replacement of selected woodpoles along San
Manuel – Manaoag – Urdaneta – San Jacinto 69kV transmission lines
Time: 7:00 AM – 9:00 AM
Affected Distribution Utility: * Parts of PANELCO III and CENPELCO
Affected areas: * Villasis, Rosales, Balungao, Sto. Tomas, Tayug, San
Nicolas, Natividad, Sta. Maria, Umingan, San Quintin, Alcala, Bautista,
Bayambang, Basista and parts of Malasiqui, Urdaneta and Asingan
Reason: Troubleshooting of 100MVA power transformer at San Manuel Substation
Time: 7:00 AM – 7:30 AM and 4:30 PM – 5:00 PM
Affected Distribution Utility: * Dagupan Electric Corporation San Jacinto Substation
Affected areas: * San Jacinto, Manaoag and San Fabian
Reason: Load shifting of Power
Normal operations will immediately resume after work completion. NGCP’s
customers and the general public are advised to take the necessary
preparations and
precautions for this scheduled interruption.
The National Grid Corporation of the Philippines (NGCP) serves notice of the scheduled shutdown of some of its transmission facilities in these areas:
Date: 24 November 2012
Time: 7:00 AM – 5:00 PM
Affected Distribution Utility: * Parts PANELCO III and CENPELCO
Affected areas: * San Manuel, Binalonan, Pozorrubio, Laoac, Mapandan and parts of Sison, Urdaneta and Asingan
Reason: Continuation of replacement of selected woodpoles along San Manuel – Manaoag – Urdaneta – San Jacinto 69kV transmission lines
Time: 7:00 AM – 9:00 AM
Affected Distribution Utility: * Parts of PANELCO III and CENPELCO
Affected areas: * Villasis, Rosales, Balungao, Sto. Tomas, Tayug, San Nicolas, Natividad, Sta. Maria, Umingan, San Quintin, Alcala, Bautista, Bayambang, Basista and parts of Malasiqui, Urdaneta and Asingan
Reason: Troubleshooting of 100MVA power transformer at San Manuel Substation
Time: 7:00 AM – 7:30 AM and 4:30 PM – 5:00 PM
Affected Distribution Utility: * Dagupan Electric Corporation San Jacinto Substation
Affected areas: * San Jacinto, Manaoag and San Fabian
Reason: Load shifting of Power
Normal operations will immediately resume after work completion. NGCP’s customers and the general public are advised to take the necessary preparations and
precautions for this scheduled interruption.
Affected Distribution Utility: * Parts PANELCO III and CENPELCO
Affected areas: * San Manuel, Binalonan, Pozorrubio, Laoac, Mapandan and parts of Sison, Urdaneta and Asingan
Reason: Continuation of replacement of selected woodpoles along San Manuel – Manaoag – Urdaneta – San Jacinto 69kV transmission lines
Time: 7:00 AM – 9:00 AM
Affected Distribution Utility: * Parts of PANELCO III and CENPELCO
Affected areas: * Villasis, Rosales, Balungao, Sto. Tomas, Tayug, San Nicolas, Natividad, Sta. Maria, Umingan, San Quintin, Alcala, Bautista, Bayambang, Basista and parts of Malasiqui, Urdaneta and Asingan
Reason: Troubleshooting of 100MVA power transformer at San Manuel Substation
Time: 7:00 AM – 7:30 AM and 4:30 PM – 5:00 PM
Affected Distribution Utility: * Dagupan Electric Corporation San Jacinto Substation
Affected areas: * San Jacinto, Manaoag and San Fabian
Reason: Load shifting of Power
Normal operations will immediately resume after work completion. NGCP’s customers and the general public are advised to take the necessary preparations and
precautions for this scheduled interruption.